This project undertook quite a lot of planning. Firstly for the safety of staff and house guests. Planned for a more quiet period of business and a short time frame, four of us finished it in 10 days.

Areas included the mezzanine level ceiling and walls then all bulkheads, balustrades, ceilings and columns in the entry level ground floor.

For the high elevated areas, we use a 6 ton knucke boom stretched to its absolute limits. To get it through the main entry doors there was 20mm of play on either side of the machine.

Colour, Barrister white throughout.